A bedroom ceiling collapse made temporary roof protection an early priority at this East McGregor Road home in Indianapolis. The project manager installed a 10-by-20-foot tarp while the insurance roof claim was being developed. The State Farm file was referred to Spartan Claims and later entered appraisal handling, before the replacement proceeded in 2022.
The house had an existing rooftop solar array, creating a separate prerequisite for the roofing crew. A requested electrical quote described removing and later reinstalling 15 panels, with removal assigned outside the roofing crew's scope. The project manager confirmed the panels were being removed on April 28.
That same update specified Malarkey Highlander shingles in Storm Gray. The roof crew completed its labor April 29, 2022. The reroof included 129 feet of hip and ridge, 127 feet of step flashing and 86.01 feet of wall flashing.
The installation scope also included two pieces of OSB decking and work at elevated and steep roof sections. The supporting roof package specified Malarkey Smart Start, RhinoRoof UDL and Tarco LeakBarrier MS300, with Black drip edge, static box vents and pipe flashings. Roof-to-wall connections formed a substantial part of the detailing alongside the new shingles.
The project manager confirmed the reroof finished in May.
Project details
- Location
- East McGregor Road, Indianapolis, Indiana.
- Property and funding
- Residential home; State Farm roof claim with Spartan Claims involvement.
- Initial protection
- Project manager confirmed installation of a 10-by-20-foot tarp.
- Solar coordination
- Removal handled outside the roofing crew; quote requested for detach/reset of 15 existing panels.
- Solar removal update
- April 28, 2022.
- Roof labor completion
- April 29, 2022.
- Shingle selection
- Malarkey Highlander, Storm Gray.
- Roof detailing
- 129 LF hip/ridge, 127 LF step flashing and 86.01 LF wall flashing.
- Decking
- Two OSB pieces included in installation labor.
- Supporting components
- Malarkey Smart Start, RhinoRoof UDL, Tarco LeakBarrier MS300, Black drip edge and Lomanco static box vents.
- Closeout
- Roofing confirmed finished May 2022.